Updated 4/13/15: Survey robot breaks down inside Fukushima No. 1 reactor in under three hours — The Japan Times

The humans are killed in one hour. The robot did not last the predicted 10 hours before it failed.

Japan Safety : Nuclear Energy Updates

Updated April 13, 2015, The Japan Times: ” A remote-controlled robot inserted to survey the inside of the No. 1 reactor at the damaged Fukushima No. 1 nuclear power plant has stopped functioning, Tokyo Electric Power Co. said.

As a first step in the utility’s effort to remove melted nuclear fuel from the bottom of the unit’s primary containment vessel, the shape-shifting robot was sent in Friday morning to find the exact location of the highly radioactive debris.

Set to cover some 20 meters of the first floor on the first day, the robot began its trip at around 11:20 a.m. but halted at around 2:10 p.m. after completing two-thirds of the route, Tepco said.

The utility said footage from the robot’s camera shows it passed an opening leading to the vessel’s basement, where the molten fuel is believed to have ended up after the core meltdowns occurred…

View original post 394 more words

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s